DODA, DECEMBER 29, 2020: To ensure timely redress of the grievance regarding electrification of the village Gonuni Tanta of Kahara Tehsil, which was raised during the LG Mulaqaat program, the DDC Doda Dr Sagar D Doifode today called upon the key functionaries of the PDD for early finalisation and execution of the plan.
During the meeting, the DDC held threadbare discussion with the officers and chalked out various important measures needed to be taken to ensure the timely completion of the work i.e electrification of the above-mentioned village.
The DDC directed the concerned to expedite the transportation of all the required material at the designated sites which includes transportation of poles, system fitting, conductor fitting etc and directed them to expedite the work.
The DDC finalized the day wise activities and asked the concerned to take all the necessary support from the Administration to reach out at the logical end without any further delay.
The DDC asked the concerned to start the work at the earliest and complete the same in a fixed timeline to provide electricity to the village.
Further, the DDC directed the SDM Thathri to review the progress of the work on daily basis, besides to ensure all the necessary support to the concerned agency.
The meeting was attended by SE JPDCL Circle Kishtwar, CPO Doda, SDM Thathri, EX En JPDCL division Doda, AEE JPDCL division Kishtwar, besides other officials.