New Delhi, 06 April 2021: Union Minister for Chemicals and Fertilizers Shri D. V. Sadananda Gowda has handed over the cheque of Rs. 813.24 crores out of total amount of Rs. 1257.82 crore to MD, HURL in respect of Interest Free Loan to Hindustan Urvarak & Rasayan Ltd (HURL) for the revival of Gorakhpur, Sindri & Barauni projects. HURL operates environment-friendly & energy-efficient Natural Gas based new Fertilizer Complexes, spurring economic growth in eastern India.
Speaking on the occasion the Minister emphasized that the release of Interest Free Loan to HURL will further strengthen its financial condition during COVID-19. It will also assist HURL to complete its project in time i.e. 2021 and boost the “AATMA NIRBHAR BHARAT” campaign of Government of India by increasing the indigenous production of Urea. The operationalization of above three plants, will reduce the import dependency on urea by 38.1 LMT per annum and it will save huge forex to the Exchequer. The capacity of each plant would be 12.7 LMT per annum. The Minister also informed that HURL projects will create huge opportunities of direct and indirect employment.
The Gorakhpur, Barurani & Sindri projects have achieved 89%, 85.1% and 86.1% progress as on 28.02.2021. Once these projects are commissioned, it would increase our domestic capacity, and further self reliance in urea production.
Government had approved Interest Free Loan (IFL) of Rs.1257.82 crore to Hindustan Urvarak and Rasayan Limited (HURL) projects situated at Gorakhpur (Uttar Pradesh) Sindri (Jharkhand) and Barauni (Bihar) on 01.08.2018. Accordingly, a Loan Agreement was executed between Department of Fertilizers and HURL on 08.09.2020. As per approval, the total amount of the IFL is to be disbursed for 3 years of IDC, details of which are as under: –
( Rs in crores)
Sl
No. |
Name of
HURL’s unit |
Amount in Ist
year IDC |
Amount in
2nd year IDC |
Amount in
3rd year IDC |
Total |
1 | Gorakhpur | 42.23 | 168.90 | 211.15 | 422.28 |
2 | Sindri | 41.58 | 166.29 | 207.90 | 415.77 |
3 | Barauni | 41.98 | 167.91 | 209.88 | 419.77 |
Total | 125.79 | 503.1 | 628.93 | 1257.82 |
The zero date, commissioning as per original / revised schedule and Overall progress as on 28.02.2021 in respect of 3 projects of HURL (Gorakhpur, Sindri and Barauni) are as under: –
Sl No. | Name of
HURL’s unit |
Zero date | Commissioning as per original schedule | Commissioning as per revised schedule | Overall progress as on 28.02.2021 |
1 | Gorakhpur | February,2018 | February,2021 | July, 2021 | 89.00 % |
2 | Barauni | May, 2018 | May, 2021 | December, 2021 | 85.1 % |
3 | Sindri | May, 2018 | May, 2021 | December, 2021 | 86.1 % |